Pierce Hall Flooring Removal Testing Results - Weekend 9/27-29

The flooring and ceilings were removed from the south wing second floor and remainder of the first floor of Pierce Hall 9/27-9/29/2019. The flooring was 9"x9" non-friable asbestos-containing tile. The ceiling materials removed did not contain asbestos. All work was done under containment to prevent infiltration of dust to adjacent areas. HEPA vacuums and air...
| Pierce Hall Renovation Updates